Skip to content
Apply Now
Our Crew Working On Landfill Project Site View

Prince William Landfill Sequence 4 Cap Construction

Client
Prince William Board of County Supervisors
Location
Manassas, VA
Services Provided
General Contractor
Market
Landfill
Our Crew Checking Water Pipe Water Flow In Project Prince William Landfill Project Site

Project Overview

Our Crew Checking Water Pipe Water Flow In Project Prince William Landfill Project Site
Our Crew Using Generator At Work
Icon Blue

Scope of Work

  • Site preparation, including stripping topsoil.

  • Installation of erosion and sediment controls, including sediment basins.

  • Installation of 1,500 linear feet of 4”/6”/8” HDPE LFG lateral pipe, 600 linear feet of 6” HDPE LFG header pipe (to replace existing pipe) and 4 LFG extraction wells.

  • Installation of 3,000 linear feet of stormwater diversion berms

  • Installation of 2,200 linear feet of 6” horizontal LFG collector pipe and wellheads, 1,900 linear feet of 6”/8” toe drain pipe, and 1,300 linear feet of 18”/30”/36” corrugated HDPE down drains.

  • Placement of 30,000 cubic yards of infiltration soil and 35,000 cubic yards of vegetative support soil from on-site borrow areas

  • Installation of the sediment basin, riser structure, and outlet piping.

  • Placement of 10,000 cubic yards of topsoil (Sargent had to amend the on-site soil with imported compost to make the topsoil).

  • Sargent crews also constructed an access bench/road across the cap area and did the final site stabilization.