The Saddleback Ridge Wind Project is a 34.2 megawatt, 12 GE’s 2.85 MW turbines.
The crews installed 14,000 linear feet of conduit trench on the ridge line, along with 2,000 linear feet of drainage pipe.
The project generated about 40,000 cubic yards of grubbings and required 90,000 cubic yards of ledge excavation. About 30,000 cubic yards of the ledge excavations are being processed into gravel, and the remainder will be used for fill.
The project included construction of a 9,000’ access road leading up to the ridge line and a 9,000’ crane path roadway with 12 pads for the wind turbines on Saddleback Ridge.