Liberty Shore Rehabilitation

Client
Private Developer
Location
South Portland, Maine
Services Provided
Shoreline rehabilitation, contaminated soil capping, shoreline stabilization, riprap installation, site grading, berm construction, and dock relocation
Market
Site Development

Project Overview

Sargent employee-owners restored approximately 450 feet of shoreline adjacent to Bug Light Park in South Portland, Maine, a site with historic connections to Liberty ship construction during World War II. The project included capping contaminated soils, removing remnants of an old dock and timber cribbing, re-establishing the shoreline subgrade, and installing heavy riprap to stabilize the shoreline. Sargent also constructed a berm to improve resilience to tidal flooding and coordinated work around tides and winter weather conditions. The 1.5-acre project required approximately 2,500 cubic yards of borrow, 1,700 cubic yards of heavy riprap, and 750 cubic yards of crushed stone.