Wide View Of Blue Ridge Regional Airport Runaway

Blue Ridge Regional Airport Runway 12-30 Pavement Rehabilitation

Client
Blue Ridge Regional Airport Authority
Location
Martinsville, VA
Services Provided
General Contractor
Market
Airports
Our Crew Working On Installing Cement-treated Base For Blue Ridge Regional Airport Runway

Project Overview

Sargent crews reconstructed the main runway at Blue Ridge Regional Airport in Martinsville, VA, which runs for 5,002 feet. We also performed comprehensive electrical upgrades for the runway and taxiways.

A major challenge on this project was the sheer quantities of material we were working with: 37,000 square yards of full-depth reclamation (10″ deep), 3,200 cubic yards of variable-depth cement-treated base embankment, 20,000 square yards of cement-treated base (8″ thick), 14,200 tons of P-401 bituminous surface course asphalt, 44,500 square yards of runway grooving, 1,400 linear feet of stormwater conveyance channels, and 18 acres of permanent seeding. In addition, we excavated 18,000 cubic yards of unclassified material.

Our Crew Working On Installing Cement-treated Base For Blue Ridge Regional Airport Runway
J.R Caskey Heavy Equipment Truck

Scope of Work

  • 37,000 square yards of full depth reclamation (10” deep)

  • 44,500 square yards of runway grooving

  • 3,200 cubic yards of variable-depth cement-treated base embankment

  • 20,000 square yards of cement-treated base (8” thick)

  • 1,400 linear feet of stormwater conveyance channels

  • 18,000 cubic yards of unclassified excavation

  • 18 acres of permanent seeding

  • 14,200 tons of P-401 bituminous surface course asphalt